Emily is the project documents controller for a multi-million dollar telecom network deployment project. Emily has just received a document from the project manager. This document contains the project stakeholders’ communication requirements for the current project phase. Emily should update which of the following project documents with this information?

A. Work breakdown structure
B. Stakeholders engagement assessment matrix
C. Stakeholder management plan
D. Stakeholder register

C. Stakeholder management plan