PMP Question 108

While rating a proposal, one of the requirements was “The proposed project manager needs to be a certified Project Management Professional, PMPĀ® ” This is an example of:

A. Constraints
B. Source Selection Criteria
C. Assumptions
D. Good practice

B. Source Selection Criteria