A project team is organized to implement a new wireless solution for a school. The team has already done the network diagrams and knows the locations that will need to be addressed in the project. The team is in the process of creating an SOW for the project as a whole and needs to add the critical pieces to the SOW to complete it and move to the next stage. Which of the following would the project team MOST likely add to the SOW?

A. Risk analysis
B. Plan to change
C. Backout plan
D. Change board approvals

Correct Answer: C