PMP Question 90

One of the stakeholders of a project initiated a change request which was then documented in the change control system. In general, who would be responsible for approving or rejecting the change request?

A. An authority within the project management team or external organization.
B. The sponsor.
C. The stakeholder who raised the change request.
D. The project manager.

A. An authority within the project management team or external organization.