PMP Question 8

You have been asked to determine the logical relationships, leads, and lags for the activities that make up a project. What would be the BEST technique to use?

A. Resource Smoothing
B. Critical Path Method
C. What-If scenario analysis.
D. Resource Leveling

B. Critical Path Method