PMP Question 54

You are in the final phase of a low cost car manufacturing project. This project, as designed, has delivered a low cost car that runs on the battery. However, to close this project, many administrative standards are required to be followed in order to avoid auditing from Government authorities. Since your organization possesses experts who have tremendous knowledge in closing procedures and standards, you would like to use them to close this project. This effort is an instance of:

A. Using enterprise environmental factors in closing the project
B. Using expert judgment in closing the project
C. Using organizational process assets in closing the project
D. Poor project management practice

B. Using expert judgment in closing the project