PMP Question 44 ( PMBOK 6th edition )

You have successfully passed your PMP exam and are leading a project to replace the storage devices in a data center. In the following week, you and your team of experts will be meeting with a storage device vendor to discuss the status of their deliverables that are due at week’s end. What management process do these activities reflect?

A. Plan Procurement Management
B. Control Procurements
C. Conduct Procurements
D. Control Resources

B. Control Procurements