PMP Question 40

After receiving some news about a delay on one of your project tasks, you reviewed the schedule to determine how it will impact the project. While there is a substantial delay on this task, it is not a critical path item and will not impact delivery of any of your milestones. Another project manager advises you to only present the milestone chart during your meeting with the project stakeholders and tell them the project is progressing as planned. What do you do?

A. Present the project as a milestone chart and advise that the progress is tracking according to plan.
B. Present the schedule in a milestone chart and disclose full details of the delay.
C. Present the schedule in a network diagram and advise that the project is tracking according to plan.
D. Present the schedule as a bar chart and advise that the project is tracking according to plan.

B. Present the schedule in a milestone chart and disclose full details of the delay.