PMP Question 35 ( PMBOK 6th edition )

Peter is a project manager who is assigned to a foreign country to manage a project. The project is a large one and comprises of smaller sub-teams, contributing to the entire project. As part of rewards and recognition within the project, Peter plans for a team award for the best sub-team. The Recognition and Rewards is associated with which of the following processes?

A. Close Project or Phase
B. Develop Team
C. Control Quality
D. Manage Team

B. Develop Team