The legal nature of the contractual relationship between a buyer and a seller requires that appropriate legal counsel be involved in the project, for specific activities. Which of the following phases requires legal counsel to be involved.

A. Control procurements
B. Plan procurement management
C. Conduct procurements
D. Each procurement management process

D. Each procurement management process