PMP Question 153

As the Project Manager for Midway Carnival Rides, you are starting off on the Define Scope process. Which of the following is a key input to the process?

A. Risk Management Plan
B. Quality Management Plan
C. Project Charter
D. Staffing Management Plan

C. Project Charter