PMP Question 138

In the earned value management technique, the cost performance baseline is referred to as:

A. Cost Measurement Baseline (CMB)
B. Performance Measurement Baseline (PMB)
C. Performance Base Value (PBV)
D. Performance Cost Baseline (PCB)

B. Performance Measurement Baseline (PMB)