PMP Question 124 ( PMBOK 6th edition )

You are working with your team and are looking at the cost risks in the project. You are your team are currently creating a tornado diagram for the project risks. This is done as a part of which of the following processes?

A. Qualitative Risk Analysis
B. Risk Response Planning
C. Quantitative Risk Analysis
D. Monitor Risks

C. Quantitative Risk Analysis