PMP Question 101

Which process of integrative project management documents the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans into a project management plan?

A. Direct and Manage Project Work
B. Monitor and Control Project Work
C. Develop Project Charter
D. Develop Project Management Plan

D. Develop Project Management Plan